Overnight construction launched for Kenmount Road intersection
The City of St. John's expects the full project to be be finished by mid-November.
Crews realigning Polina Road, upgrading sewer in front of Avalon Mall
Expect a few noisy nights on Kenmount Road in St. John's this week.
The city is starting overnight road construction in the area of Polina Road and the Avalon Mall, where workers are realigning the road and upgrading the storm sewer.
Work has been ongoing during the day and evening since July, but until Sunday, crews have the green light to run their equipment all night long.
Crews will work overnight Oct. 3-7. The schedule for more overnight work through the rest of the month hasn't been set yet.
The full project should be finished by mid-November.