PEI

Charlottetown Airport asks for patience during runway construction

Charlottetown Airport is asking travellers to be patient as construction on a new main runway continues, adding there has been a slight increase in cancellations and delays since the work started this spring.

Officials report slight increase in cancellations and delays

Construction on the main runway at the Charlottetown airport is about 50 per cent complete so all flights are taking off and landing from the secondary runway. (Jessica Doria-Brown/CBC)

Charlottetown Airport is asking travellers to be patient as construction is about halfway complete on the airport's new main runway.

Airport officials confirm there has been a slight increase in cancellations and delays since the work started this spring, but say they've received no formal complaints since a particularly bad day of weather back in April.

CEO Doug Newson says disruptions have been minimal — in the last three months, the airlines completed about 97 per cent of their flight schedules, and not all disruptions were linked to the construction. 

"It's regrettable when there are flights that get disrupted, but I think overall it's gone very well," said Newson.

'Short-term pain'

Newson pointed out the new runway is a "once-in-30-year project," adding "there is a bit of short term pain."

Airport CEO Doug Newson says 96.5%-97% of flight have operated for this summer season, and generally the numbers are closer to 98%. (Jessica Doria-Brown/CBC )

"But once this project is completed we'll have two fairly new runways and we won't be doing any major repair work for the foreseeable future," he said. 

During construction on the main runway all planes are taking off and landing using the airport's new secondary runway. It doesn't have the same navigation capabilities as the main landing strip, so landing in fog or low cloud can be more difficult.

"But we certainly want people to book with assurances that our flights are going to operate and the airlines will get them here as quickly and safely as possible."

Newson said construction is on schedule thanks to the hot, dry weather.

Paving has started on the main runway at the Charlottetown Airport and construction is on schedule to wrap up by mid-October, officials say. (Jessica Doria-Brown/CBC)

This week crews are starting to lay down asphalt for the new runway, which they hope to complete by September.

The next step will be to paint lines and run tests.

The $18 million project is set to be completed by mid-October.

More P.E.I. news

ABOUT THE AUTHOR

Jessica Doria-Brown

Videojournalist

Jessica Doria-Brown is a videojournalist with CBC in P.E.I. Originally from Toronto, Jessica has worked for CBC in Newfoundland and Labrador, New Brunswick, and Ontario.